Milestone | Planned deadline | Actual deadline | Description of the Milestone | Comments |
---|
M0 | date as initially planned | date as really committed | - Declaration of participation in the simultaneous release
- The initial version of Increment Blueprint presented and discussed, discussed and approved by TSC
- Release Scope Overview updated accordingly, agreed, approved by TSC
- The initial version of the Release Plan for the project presented
- Dependencies between projects identified
- TSC Approvals of participation of particular projects
| problems, decisions, reasons for the delay, etc |
---|
M1 |
|
| - all dependencies between projects discussed and agreed
- The final version of Increment Blueprint and the Release Plan for the project discussed and approved
|
|
---|
M2 |
|
| - Design fully provided, agreedÂ
- Documentation started
- Feature tests started
- Feature/Functionality Freeze
|
|
---|
M3 |
|
| - External API available for beta-tests
- Documentation in progress
| M4 | - Tests in progress
- API Freeze
|
|
---|
M4 |
|
| - all functionality and APIs available for testing
- Code freeze - only bug fixing allowed
|
|
---|
RC0 |
|
| - Release candidates agreed, approved, tested
- release branch cut off - branch stabilization from now on
- Release Candidates freeze
M5 |
|
---|