Planned deadlines

MilestonePlanned deadlineActual deadlineDescription of the MilestoneComments
M0date as initially planneddate as really committed
Declaration
  • Blueprint proposal represented as a Jira EPIC ticket
  • Feature lead assigned to Jira Epic ticket - declaration of participation in the simultaneous release
  • The initial version of Increment Blueprint stored on github/tf-spec/Release folder,
  • The blueprint presented
and discussed
identifiedTSC Approvals of participation of particular projects
  • /components/areas identified
problems, decisions, reasons for the delay, etc
M1

  • All dependencies between existing functionality and requested change/feature discussed and agreed by PTL and related approvers (based on Modules/Commiters)
  • Jira Epic ticket broken down into stories in related Jira project (backlog, plan) - presented and discussed on TWS meeting
  • The final version of Blueprints, Release Scope and Release Plans for participating projects discussed and approved by approvers

M2

  • Technical design fully provided, agreed (documentation on the Confluence/github/tf-spec available)
  • Jira Epic ticket updated with link to technical design
  • Documentation started
  • Feature tests started
  • Feature/Functionality Freeze - Technical Design approved by relevant approvers (Modules/Commiters)

M3

  • External API available for beta-tests
  • Jira Epic ticket updated with information about API availability (documentation link - tf repo)
  • Documentation in progress
  • Tests in progress
  • API Freeze confirmed by Feature Lead (comment on Jira Epic ticket with repo/commit ID link)

M4
M5


  • all functionality and APIs available for testing
  • Jira Epic ticket updated with information about final API documentation, executed UI tests documentation
  • Documentation provided - confirmed by Documentation project PTL
  • Code freeze confirmed by Feature Lead (comment on Jira Epic ticket) - only bug fixing allowed

RC0

  • Release candidates agreed, approved, tested
  • System tests conducted, quality confirmed by CI/CD PTL (should we have some QA? Security?)
  • Final documentation provided, reviewed, approved by Documentation PTL
  • Marketing information provided to Marketing Advisory Council - confirmed by Brandon Wick?
  • release branch cut off - branch stabilization from now on
  • Release Candidates freeze, confirmed by PTL and TSC(?)

Deployment

official deployment executed




Planned scope

ProjectScopeDependencies
Project Name (link)Overall description of the project's increment in the particular release
  • Dependent on: projects, on which this increment relay on
  • Affect: projects which depend on this increment