Planned deadlines
Milestone | Planned deadline | Actual deadline | Description of the Milestone | Comments |
---|
M0 | | date as really committed | - Declaration of participation in the simultaneous release
- The initial version of Increment Blueprint presented, discussed and approved by TSC
- Blueprint proposal represented as a Jira EPIC ticket
- Release Scope Overview updated accordingly, agreed, approved by TSC
- The initial version of the Release Plan for the project presented
- Dependencies between projects/components/areas identified
- Participating projects and initial Release scope approved by TSC
| - Not all Tech Leaders pointed by Juniper are registered on Tungsten Fabric (lack of login, contact)
- Description of blueprints not available for TF (links refer to Juniper side)
|
---|
M1 | |
| - all dependencies between projects discussed and agreed
- The final version of Increment Blueprints, Release Scope and Release Plans for participating projects discussed and approved by TSC
|
|
---|
M2 | |
| - Technical design fully provided, agreed
- Documentation started
- Feature tests started
- Feature/Functionality Freeze
|
|
---|
M3 | |
| - External API available for beta-tests
- Documentation in progress
- Tests in progress
- API Freeze
|
|
---|
M4 | |
| - all functionality and APIs available for testing
- Code freeze - only bug fixing allowed
|
|
---|
RC0 | |
| - Release candidates agreed, approved, tested
- release branch cut off - branch stabilization from now on
- Release Candidates freeze
|
|
---|
Planned scope (current state based on Jira assignment to FixVersion R2011)
Release board - https://jira.tungsten.io/secure/RapidBoard.jspa?rapidView=5&projectKey=TFF
Jira |
---|
server | Tungsten Fabric |
---|
columns | key,summary,type,created,updated,assignee,status,resolution |
---|
maximumIssues | 20 |
---|
jqlQuery | fixversion in (R2011) order by Key ASC |
---|
serverId | 82691efe-91a0-3cff-8e71-932ce5d4700b |
---|
|
...