| problems, decisions, reasons for the delay, etc |
M1 |
|
| - All dependencies between existing functionality and requested change/feature discussed and agreed by PTL and related approvers (based on Modules/Commiters)
- Jira Epic ticket broken down into stories in related Jira project (backlog, plan) - presented and discussed on TWS meeting
- The final version of Blueprints, Release Scope and Release Plans for participating projects discussed and approved by approvers
|
|
---|
M2 |
|
| - Technical design fully provided, agreed (documentation on the Confluence/github/tf-spec available)
- Jira Epic ticket updated with link to technical design
- Documentation started
- Feature tests started
- Feature/Functionality Freeze - Technical Design approved by relevant approvers (Modules/Commiters)
|
|
---|
M3 |
|
| - External API available for beta-tests
- Jira Epic ticket updated with information about API availability (documentation link - tf repo)
- Documentation in progress
- Tests in progress
- API Freeze confirmed by Feature Lead (comment on Jira Epic ticket with repo/commit ID link)
|
|
---|
M4 |
|
| - all functionality and APIs available for testing
- Jira Epic ticket updated with information about final API documentation, executed UI tests documentation
- Documentation provided - confirmed by Documentation project PTL
- Code freeze confirmed by Feature Lead (comment on Jira Epic ticket) - only bug fixing allowed
|
|
---|
RC0 |
|
| - Release candidates agreed, approved, tested
- System tests conducted, quality confirmed by CI/CD PTL (should we have some QA? Security?)
- Final documentation provided, reviewed, approved by Documentation PTL
- Marketing information provided to Marketing Advisory Council - confirmed by Brandon Wick?
- release branch cut off - branch stabilization from now on
- Release Candidates freeze, confirmed by PTL and TSC(?)
|
|
---|
Deployment |
|
| official deployment executed |
|
---|