Note: please refer to previous discussion Business-level Requirements for TF Release Process

Initially, due to the absence of release definition and process, community release needs to be aligned with some Contrail commercial release. Once the Community establishes its own independent release definition and process, all commercial releases including contrail can be aligned to community release.

This alignment is necessary to allow migration between the community and commercial release. As long as this alignment is maintained, Commercial release can follow any other release frequencies.

Aligning with Contrail commercial release to begin with we have following options:

  1. We do a release out of old branch R1911 now to bridge the gap from the last community release of r5.1 and look forward to do next release in June, 2020 aligning with Contrail release of June - 
  2. We skip the releases between r5.1 and R2002, and look forward to do next release in March, 2020 aligning with Contrail release of March


The purpose of the release process

The Release Process is dedicated to creating a plan and then following and monitoring that plan to deliver an increment to the product. It is extremely important, especially in a community where there are lots of developers from different companies, countries, to have a common understanding of what and how we would like to achieve. The release plan will help us to coordinate our efforts to achieve agreed goals and to deliver proper, coded, tested, and working as an expected increment of product. To achieve that, we need to act in accordance with agreed rules, time schedule, and milestones.

Prerequisites

All who would like to attend community effort and contribution must follow bellow prerequisites:

Release Process

The release process is outlined as follows

  • Invitation of proposals for features, enhancement requests
  • Blueprints/Design/Architectural approval cut-off date (4 months before release date)
  • Code delivery cut-off date (2 months before release date)
  • Branch cut-off date (1 month before release date)
  • Stabilize the branch and build daily builds for 1 month
  • Release the stable build as Community Release
  • Build weekly/bi-weekly if any change committed to the branch

Release Cadence, Life Time & Support

The initial release cadence is planned for every 6 months. The initial release process is waterfall-based, but the Community intends to move into a more agile approach in the future.

The Community intends to actively support any release for up to 9 months, where any bug fixes will be committed and made available.