The initial version of the Release Plan for the project presented
Dependencies between projects/components/areas identified
Participating projects and initial Release scope approved by TSC
Not all Tech Leaders pointed by Juniper are registered on Tungsten Fabric (lack of login, contact)
Description of blueprints not available for TF (links refer to Juniper side)
Features leaders not registerd in LF/Jira
Blueprint approval process not agreed
Blueprint template not agreed
Features leaders not registerd in LF/Jira
Blueprint approval process not agreed - rework, approvers still needed
Blueprint template agreed, but moved rather to tf-specs repo
Most of blueprint presented/approved (15 out of 19)
TFF-12 and TFF-15 will be discussed clarified at
M1
All dependencies between existing functionality and requested change/feature discussed and agreed by PTL and related approvers (based on Modules/Commiters)
Jira Epic ticket broken down into stories in related Jira project (backlog, plan) - presented and discussed on TWS meeting
The final version of Blueprints, Release Scope and Release Plans for participating projects discussed and approved by approvers
M2
Technical design fully provided, agreed (documentation on the Confluence/github/tf-spec available)
Jira Epic ticket updated with link to technical design
Documentation started
Feature tests started
Feature/Functionality Freeze - Technical Design approved by relevant approvers (Modules/Commiters)
M3
External API available for beta-tests
Jira Epic ticket updated with information about API availability (documentation link - tf repo)
Documentation in progress
Tests in progress
API Freeze confirmed by Feature Lead (comment on Jira Epic ticket with repo/commit ID link)
Critical - must be aligned with Juniper timeline
M4
all functionality and APIs available for testing
Jira Epic ticket updated with information about final API documentation, executed UI tests documentation
Documentation provided - confirmed by Documentation project PTL
Code freeze confirmed by Feature Lead (comment on Jira Epic ticket) - only bug fixing allowed
From now on, discussion about release candidates may be conducted
RC0
Release candidates agreed, approved, tested
System tests conducted, quality confirmed by CI/CD PTL (should we have some QA? Security?)
Final documentation provided, reviewed, approved by Documentation PTL
Marketing information provided to Marketing Advisory Council - confirmed by Brandon Wick?
release branch cut off - branch stabilization from now on
Release Candidates freeze, confirmed by PTL and TSC(?)
delay with testing - so date is moved till mid of December
Release notes, documentation, diff between previous version are needed